DPWH Caraga updates on the status of construction of the quarantine facilities (QFs) in the region. These are the six 50-bed capacity QFs with a budget of P25M per project which is expected to be completed on the first week of September 2020:
1) QF in Brgy. Baan Km3, Butuan City
2) QF in Brgy. Cagniog, Surigao City
3) QF in Brgy. Silop, Surigao City
4) QF in Nasipit, Agusan del Norte
5) QF in Bunawan, Agusan del Sur
6) Rehab/Improvement of three units building for QF in Km. 5, Tabon, Bislig City, Surigao del Sur
(PIA 13 | RPN DXKS Surigao)