NGCP Is Done With Upgrading Activities At Placer Substation

0
72

The following lines are now energized:

  1. Placer-Madrid 69kV Line at 12:41 PM
  2. Placer-Tubod 69kV Line at 4:01 PM

On the other hand, we have pending energization of Placer-Surigao 69kV Line since SURNECO is not yet done with their “ride-on” maintenance activities.

We finished activities ahead of schedule.

Thanks and keep safe!

(Source: NGCP | Kristoffer Abellanosa)

Leave a Reply